The 100% rule might be broken if: (check ALL that apply)
The sum of the work at the child level equals 100% of the parent
An item appears in the WBS in more than one place
The WBS covers all of the deliverables
Team members are not giving 100% effort 100% of the time
The WBS covers deliverables that are out of scope