a) What proactive actions do you believe Amanda and Josh could have taken to keep the project on schedule?
b) Given the project has spent the $2.3M budget, what is your recommendation regarding the nine (9) units that have to be installed? From a cost perspective, what are the options available to Amanda and Josh?
c) A key council member wants assurance that the project will be completed in three (3) months or less. How will you address this individual?
d) Amanda and Josh are concerned that people and equipment assigned for the project are sometimes unavailable when scheduled. What are reasons this problem might be surfacing during the execution phase?
e) Based on what you learned from this Assignment, what are five (5) lessons learned that you can share with the project managers.